Description
Ⅰ、 Structural characteristics and working principle
The YGM-110 multifunctional oil pipe anchor adopts a spring energy storage anchor structure. When the multifunctional oil pipe anchor is lowered into the wellbore and immersed in the well fluid, the release pin of the energy storage spring is melted, and the compressed energy storage spring pushes the card holder and card holder upward to bite on the inner wall of the casing, playing the role of anchoring the pipe string. When the pipe column is lifted, the central pipe is raised, the unsealing shear nail is cut off, and the lower joint is inserted into the sealing sleeve relatively downwards to retract the clamp support and clamp downwards, and the anchoring is released.
Ⅱ、Structural composition
The YGM-110 multifunctional oil pipe anchor is mainly composed of components such as an upper joint, clamps, clamps, soluble pins, energy storage springs, center tubes, spring sleeves, sealing sleeves, sealing pistons, unsealing shear pins, and lower joints.
Ⅲ、Main technical indicators
| Parameter | Values |
| Maximum outer diameter | φ110mm |
| Minimum inner diameter | φ60mm |
| operating pressure differential | 35Mpa |
| temperature resistance | 130℃ |
| Soluble pin dissolution time | 16h-24h |
| Unseal the nail cutting load | 8t-10t |
| Connecting thread | 2 7/8EUE |
| Applicable inner diameter of casing | φ118.6—φ124.3mm |
Ⅳ、 Main purpose
Used for anchoring various measures of casing perforation completion strings and oil pump production strings.
Ⅴ、 Requirements for loading, unloading, and storage
- During loading and unloading, attention should be paid to placing them flat and upright, without heavy pressure, and collisions are strictly prohibited;
- Be careful not to damage the slip;
- It is strictly prohibited to come into contact with corrosive substances such as acid, alkali, salt, etc;
- Store in a dry and ventilated place, avoiding rain and moisture;
- Stay at least 1.5 meters away from heat sources.
Ⅶ、 Operating procedures
- Select the appropriate specifications and models for the multifunctional tubing anchor based on the design.
- Choose a suitable well gauge to connect the well to 10-20 meters below the oil pipe anchor seal section.
- Lower the casing scraper and repeatedly scrape 5-7 times at a distance of 10 meters above and below the checkpoint.
- Anchor the tubing string, inspect the multi anchor energy tubing anchor as required, confirm its specifications and models are correct, and connect it to the wellbore according to the construction design tubing string diagram. During the process of lowering the tool into the well, it is forbidden to lift or place the pipe column forcefully to prevent damage to the tool during the process.
- Magnetic positioning depth calibration and adjustment of anchoring column depth.
- Wash the well and fill the wellbore with active water.
- Anchoring the tubing string: After adjusting the depth of the tubing string, the next step of construction can be carried out. The anchoring of the multifunctional tubing anchor will be automatically completed during the immersion process of the wellbore liquid. When the soluble pin dissolves, the energy storage spring will work to push the card holder and card holder upward, and the card holder will extend and bite on the inner wall of the casing, playing the role of anchoring the tubing string.
- Anchor release of pipe column: Lift up the central pipe, break the unsealing shear nail, retract the relative movement force of the upper and lower joints of the slip, release the anchor, and lift up the pipe column.
Ⅷ、 Construction precautions
- Before lowering the tubing string into the well, accurate measurements must be taken to ensure that the multifunctional tubing anchor is lowered to the design position. If necessary, adjustments to the short section should be prepared.
- Clean the threads of the downhole string, apply sealing grease, wrap sealing tape, and tighten the threads to the recommended torque during the downhole process.
- During the process of lifting and lowering the pipe column, self sealing and other anti fall devices should be installed at the wellhead.
- Control the drilling speed and maintain a constant speed (recommended 20 pieces per hour).
- Safety and environmental protection shall be implemented in accordance with relevant regulations.